Building on the Past: Keeping the Dream Alive
No items found.

Building on the Past: Keeping the Dream Alive

First in a series on the restoration of Ezra & Mary's 166-year-old home

My Dad always had one BIG dream: Restore the old Ezra T. Clark home and property to its former glory. When he purchased it in the late 60s, it had been divided into three apartments quite nicely. A result of 3 entrances and neat 3 sections, each with its own front and back entrances.

Over the next 40 years, my parents would diligently raise 9 children: 8 boys and one girl in this old house. Most of the time it looked like an episode of the same name. –with at least one room in repair or under renovation.

Above the mantle always hung the steely-eyed Ezra & Mary Family portrait. One girl, 8 boys. What I didn't know is that Mary's oldest had died returning fom his mission and that Elizabeth had married and divorced twice. Polygamy was a lot harder than Ezra, Mary and Susan and Nancy mad it look. Marriage was hard enough.

Funding Needed - In Progress
Updates edited
Oct 30, 2022
• Removed temporary porch roofs added in 1990s and 2000s.
• Restored 1914 hip-style porch roof. Framing and sheathing is completed and weatherproofed for winter, awaiting installation of historic sawn cedar shingles.
• New underground power line trenches dug and conduit added.
Nov 22, 2022
• Entire east wing roof and second level roof weatherproofed for winter.
• Sewer line scoped to yard.
Jan 5, 2023
• Last three remaining rooms cleared of carpets, exposing wood and asbestos floors.
• Sewer scoped to street.

Feb 27, 2023
• Sewer line in parking strip exposed and mystery solved: Pipe drilled through by cable company.
• Flower beds cleared of volunteer trees


March 20, 2023
• Sewer lateral repaired in west yard and near front sidewalk.
• Privet Lodense hedges replanted, exisring hedges pruned to stimulate growth.
• East garden planted.
• New landscape irrigation system added for front yard.

May 23, 2023
• 2,000 SqFt of Grass in Parking Strip replanted
• 400 SqFt of Grass behind Hedges replanted

June 14, 2022
• Made wonderful discovery that entry hall ceiling originally opened to second level with wrap-around stairs. Plans will be adjusted and additional research conducted to restore this fabulous feature.

• New Pex culinary water lines added for main kitchen and bath

• Electric wiring updated on Front Porch to restore lanterns and lighting.